Summary

The board discussed a $2,038,783 construction contract with SSP Industries to install permanent zebra mussel mitigation infrastructure at the North Lake Water Treatment Plant raw water intake.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 11, 2026.

Impact analysis

💰Financial impact

The contract is valued at $2,038,783.00.

✅Who benefits

City water customers who rely on uninterrupted raw water intake and treatment from North Lake.